Slide 57 of 62
Notes:
- XO’s experience as a DCA on a conventional CV, and equally his lack of experience with nuclear CVN engineering operations, led to his failure to consider the possibility the CVN was backing as part of engineering plant control drills.
- The DDG’s involvement (or lack there of) was rejected as a significant cause.