Milestone Schedule
Acquisition Strategy Approved 20 Jul 98
Draft PRDA / Model Agreement 22 Jul 98
Industry Comments on Draft Solicitation Documents 05 Aug 98
CBD PRDA Solicitation Issued 24 Aug 98
Contractor Proposals Due 23 Sep 98
Technical Evaluations of Proposals Complete 09 Oct 98
Recommendations to SSA/Decision 15 Oct 98
Negotiations Complete 23 Nov 98
Section 845 Agreement Awarded 15 Dec 98