TGP Options Presented Mar 99
Option 1 Option 1 Option 2 Option 3 Option 4 CCIP Baseline
QRC-24 QRC-24 50T5+ M2+ M3+ M3+
SW SW/HW HW/SW HW/SW HW/SW SW
Costs $7.5M $14.6M $29.2M $18.6M $13.3M $3M
Schedule 7 mo 17 mo 23 mo Jan 02 Oct 03 Sep 03
Impact DTS/Nuc DTS/Nuc DTS/Nuc M3+ delay M3+ delay None
M2/40T6 Degr HTS M3+ delay 6 mos 2 mos
Risk Low Med High High Med Low