Currently in month 19 of 24-month Phase 0 Concept Exploration
ORD in final Services’ coordination for approval
OSD/Program Office preparing cost estimates / assessments
Integrated Product Team developing acquisition strategy and program management documents for PDRR
Continued synchronization with GATM, NAVWAR, and FAA included in PDRR planning
JROC validation of ORD planned for Feb 98
Milestone I review planned May 98