Schedule Development
- Post-deployment Maintenance Period (1 month)
- ROH/SRA (9 weeks to 9 months)
- Basic (6 months)
- Intermediate (4 months)
Note: Gain an early appreciation for the “lead” scheduler for each period. Stay in front of the issues with the ISIC. Find areas of flexibility and beware of the rules.
- Post deployment Lve/Upk mandated to 30 days
- ROH/SRA lenght determined by contract
- Basic schedule is more flexible
- Intermediate Optempo driven by C2X and FLTX